#RoadWork will start September 13, 2021.

The City of King City will be performing pavement rehabilitation of certain streets within the City.

During construction, it will be necessary to close the street partially or completely to vehicular traffic during construction work hours due to safety concerns. No street closure is expected to last more than 12 hours at a time. Street parking will also be restricted. "No Parking" signs will be posted along the street 3 days in advance and will be enforced by the Police Department.

#RoadWork will start September 13, 2021. Learn more at bit.ly/3BU8Gyh

The start dates are:
SCHEDULE "A" SW 116th AVE – 9/13/2021
SCHEDULE "B" BEXLEY LN – 10/4/2021
SCHEDULE "C" MATADOR LN – 9/20/2021
SCHEDULE "D" MAJESTIC – 9/23/2021

Go to the King City Road Closures Helper App

Weather and other natural events can affect paving activities.